Executed by ANUBX
Wet lay-up preservation of an 8-inch multiphase flowline
A 1.6 km carbon steel flowline for an Egyptian operator was kept in wet lay-up for 159 days. Corrosion coupons retrieved at the end showed an average rate of 0.0154 mm/y.
- Asset
- 8-inch multiphase flowline, 1.6 km, carbon steel
- Client
- An Egyptian operator
- Lay-up
- Wet lay-up, chemically treated and pressurized
- Period
- December 2025 to June 2026, 159 days
Scope
The flowline carries wet gas and condensate. After a successful hydrostatic test it was placed in wet lay-up straight away.
The line has a buried low point and no permanent pig launchers or receivers, which shaped both the preservation and the later return to service.
ANUBX delivered the specifications, the execution procedure, consultation during execution, inspection, monitoring, coupon retrieval and the close-out report.
Method
- Treat the fill waterAn oxygen scavenger, a film-forming corrosion inhibitor and a biocide were dosed into the lay-up water.
- Pressurize and holdThe filled line was pressurized and left under positive pressure for the lay-up period.
- Monitor with couponsTwo carbon steel corrosion coupons were installed at the inlet on the first day.
- Retrieve and measureAfter 159 days the coupons were retrieved, cleaned to ASTM G1 and weighed by the operator's own laboratory.
Results
Both coupons fell in the band that NACE/AMPP SP0775 classes as excellent corrosion control.
| Coupon | Exposure | Rate (mm/y) | Rate (mpy) | Class |
|---|---|---|---|---|
| Coupon 1 | 159 days | 0.0147 | 0.579 | Low |
| Coupon 2 | 159 days | 0.0161 | 0.634 | Low |
| Average | 159 days | 0.0154 | 0.606 | Low |
- A black protective film formed on the coupons within 24 hours of filling.
- The film was still intact and adherent at retrieval, with no dominant red rust.
- The two coupons agreed closely, which points to low, uniform corrosion.
- Excellent: Up to 1 mpy. Measured average: 0.606 mpy
- Acceptable: 1 to 3 mpy
- Marginal: 3 to 5 mpy
- Unacceptable: Above 5 mpy
Corrosion rate (mpy)
Bands per NACE/AMPP SP0775: up to 1 mpy excellent, 1 to 3 acceptable, 3 to 5 marginal, above 5 unacceptable.
Photo record




What the client received
- Preservation specifications and the execution procedure.
- Consultation during execution, with inspection and monitoring.
- Coupon retrieval and a close-out report with the data, photographs and engineering assessment.
- A return-to-service sequence with a sampling plan: drain, fresh-water flush, low-point liquid removal, nitrogen drying and a staged first gas-in.
Standards applied
- ASTM G1: coupon cleaning
- ASTM G31: corrosion rate calculation
- NACE/AMPP SP0775: coupon monitoring and classification